Energy Power Evolution is a "switching" battery charger capable of electronically controlling all its phases thanks to an advanced microcontroller.
It was designed to recharge liquid lead-acid batteries and gel lead-acid batteries. It allows you to reduce charging times and optimize charging by applying a stabilized voltage of 14.6V to the battery terminals, even with insufficient engine battery voltages. The maximum current controlled by Energy Power is 30-35 A. Additionally, the Evolution is capable of performing charge maintenance, below a current threshold, by decreasing the voltage applied to the battery terminals, thus avoiding further stress to the battery.
Warning: Energy Power Evolution must be used to charge a single battery Dual Battery switch of 100 Ah or max 120Ah. To charge 2 batteries, it is necessary to install the "Dual Battery Switch" in order to distribute the charging current and keep it below the safety threshold.

Electrical Characteristics
Input Voltage: from 10….15V.
Output Voltage: 14.6 V stabilized at 30 A.
Activation: D+ command with adjustable value
Maximum Supportable Current: 30 A at 13.5 V.
Input Current Protection: 40A blade fuse.
Output Current Protection: 35° blade fuse.
Diagnosis: Optical and acoustic via bicolor LEDs and buzzer.
Interface: RJ45 plug connector for remote display with voltage display
and current during the charging phase.
Charging Phase: > 3A
Maintenance Phase: < 2A
Forced air cooling during charging and overcharging. Not active during maintenance phase.
Manual reset switch.
Advanced management and control by microprocessor.

Why install Energy Power Evolution

If we start the vehicle, the vehicle's alternator should simultaneously charge the Engine Battery and the Service Battery, being connected to each other by the paralleling relay or the service control unit. However, when we turn on: the projector headlights for the trip, the refrigerator and some small utilities in the living compartment, we will notice that the voltage measured across the Engine Battery will drop around 14.0V or even less; on the Service Battery the voltage can be about 0.5 V lower, obtaining a voltage of about 13.5V, insufficient for charging our service battery. In these conditions we are unable to comply with the charging parameters required by battery manufacturers and therefore we risk arriving at our destination with a precarious energy resource and activating the dangerous "SULFATION" of the battery

How Energy Power Evolution works
After 30 seconds from starting the vehicle's engine, the Energy Power Evolution draws energy from the Engine Battery, charged by the alternator, and transfers it to the Service Battery taking into account the charging parameters declared by the manufacturers: from 14.4V to 14.8 V (accumulators called slow discharge).
To verify correct operation, you can connect through an RJ45 cable a Control Panel capable of displaying, alternately every 5 seconds, the value of the voltage and charging current of the Service battery. The same also shows the 2 LEDs that indicate the operation diagnosis during battery charging.

Description of Operation
When the vehicle is turned on, the Energy Power Evolution enters stand-by for 30 seconds to allow the vehicle's control unit to perform its own tests, after which if the system is correct, the test is performed
optical and acoustic of the system with the activation of LEDs, display and buzzer. The electrical input and output parameters from the Energy Power are immediately displayed after. Normal operation is confirmed by the green activation of both LEDs.

Charge maintenance
When the charging current of the connected battery is less than 2.0 A, the Energy Power Evolution begins the charge maintenance phase by decreasing the voltage value in accordance with the curves of the graphs declared by the manufacturers.

Operation of the cooling fan
The fan has the function of cooling the internal circuit of the Energy Power Evolution, it is always active except during the maintenance function.

LED related to Engine Battery
Solid green indicates normal operation Flashing red indicates that the engine battery does not have sufficient energy to charge the service battery and the output current from the Energy Power Evolution is limited to prevent damage to the source battery. Solid red with acoustic buzzer warning indicates that there is a complete lack of input energy to the Energy Power Evolution, check the protection fuse

LED related to Service Battery
Solid green indicates normal operation Flashing red indicates that the output protection fuse may be blown or the load may need a higher current than the rated current of the Energy Power Evolution (check current and voltage on the display).

Description of the Terminal BlockTerminal block energy power evolution
Faston D+: connection of the Energy Power Evolution activation signal

40 A Fuse: Input Current Protection
35 A Fuse: Output Current Protection
Green Connector: see connection diagram




Description of Rear Side Controls
LED In Battery: Diagnostic LED regarding incoming current operation.

LED Out Battery: Diagnostic LED regarding charging current operation.
Remote Display: RJ45 connection for Display showing charge values.

Factory Configuration:
With Energy Power Evolution Off:
Make sure that Dip 1 and Dip 2 are in the OFF position.
Start with 30" delay with D+ > 13.5 Volts.